FAZA Cladding Installation Guide 

Store cladding packs flat and out of direct sunlight. (Only when temperature is between 5°C – 25°C)

  1. Fix cladding to minimum 25mm deep battens at maximum 400mm centres. !
  2. Provide minimum 25mm ventilation cavity from the bottom to the top of the installation. (this will be achieved by using 25mm cladding battens) 
  3. Do not close the ventilation space at the top or bottom
  4. Start the cladding at a minimum of 150mm from the ground.
  5. Allow an expansion gap of 5mm between planks at board ends
  6. Fix using corrosion resistant 30mm x 3.5mm washer head screws
  7. Where possible, position screw at the centre of the fixing groove.
  8.  Begin fixing at the centre of the cladding and work towards the ends. 
  9. Clean cladding with a mild detergent that does not contain solvents or aggressive cleaning agents. Pressure    washing is acceptable at half power. 
  10. A Horizontal Break should be provided in the following circumstances: Where a cladding panel exceeds 6m in height, a horizontal break should be provided by use of a drip trim to facilitate ventilation openings above and below the break.  Where the building regulations require a cavity barrier for the purposes of fire separation. Specific fire-stop proposed should be checked against local regulations. which may vary from region to region. 
  11. A vertical break is sometimes required to comply with building regulations or at Existing movement joints. 

Download our technical documents